Loveland Downtown Partnership Home Page
Loveland Colorado Downtown Partnership

The Foundry, Downtown Loveland Colorado

Click here for The Foundry Updates See LIVE Foundry Cam here!  Visit The Foundry Loveland here

 

The Foundry is where bold creativity and daring ideas take shape. In the core of the Sweetheart City, The Foundry will be a work of art in its own right providing a strong foundation for the revitalization of Loveland’s historic downtown. Three city blocks will soon transform into a movie theater, apartments, a hotel, retailers, a community plaza, and parking in downtown Loveland. 

The Foundry will transform three city blocks in the heart of downtown Loveland into an epicenter of entertainment. The project will include a hotel, two mixed-use buildings, a theater, a community plaza, and a parking garage. Each of the mixed-use buildings will have retail and multifamily components providing much sought-after retail space along Cleveland and Lincoln avenues as well as 155 urban living units.

Bold Creativity and Daring Ideas - Retail available 2018

Partners


City of Loveland
Brue Baukol
Loveland Downtown District
Tenants
Local Businesses


Brinkman Construction
OZ Architecture
Waypoint Real Estate

 


The FOUNDRY - Updates

The Foundry - UPDATE August 2017 Monthly Report

Click Here For August 2017 Monthly Report

The Foundry - UPDATE August 27, 2017 - September 2, 2017

Sitework and Buildings:

  • Garage foundation walls being installed along gridline A.
  • Placement of Garage lower level columns along gridlines C and D.
  • Excavation for the dewatering wet well and caisson installation began Caisson installation for the dewatering wet well began
  • Lincoln Avenue Building first floor post tensioned slab complete. Second level masonry began.
  • Dewatering pipe, fabric and filter rock installation began

Environmental:

  • Construction dewatering continues with regular sampling.
  • Planning for restoration of VCUP required monitoring wells PR3, PR1 and LC4 damaged during early phases of construction

Right of Way:

  • No work completed this week.

Other:

  • Garage perimeter foundation waterproofing
  • Garage dewatering system design received and is under City review
  • Final 100% CD set of garage plans received.
  • 90% Plaza review plans received.

Upcoming work:

  • Formwork and wall installation for south and east sections of garage lower level.
  • Installation of dewatering wet well vault caissons, walls and deck.
  • Installation of first garage slab placement.
  • Beginning of second floor of the Lincoln Building.
  • Garage precast fabrication begins September 15, 2017.

The Foundry - UPDATE August 13, 2017 - August 19, 2017

Sitework and Buildings:

  • Garage foundation walls being installed
  • Work has started on Lincoln Avenue Building first floor formwork and reinforcing for post tensioned deck
  • Dewatering planning for dewatering wet well vault
  • Garage stairwells waterproofed and backfilled

Environmental:

  • Construction dewatering continues with regular sampling
  • Planning continues for restoration Brownfields/Voluntary Cleanup Plan requiring monitoring of wells that were damaged during early phases of construction

Upcoming work:

  • Formwork and wall installation for east, north and west section of garage.
  • Completion of design for garage dewatering and filtration system.
  • Installation of dewatering wet well vault caissons, walls and deck.
  • Installation of underslab dewatering collection pipes
  • Installation of first garage slab placement
  • Movie theatre planning meetings and concept review of drawings continues.

The Foundry - UPDATE July 23, 2017 - July 29, 2017

What will you see?

  • Caisson construction for the garage was completed.
  • Lincoln Avenue Building first floor columns are complete except remaining entry column on northeast corner.
  • Garage wall formwork began.
  • Garage stairwell and elevator mat slabs were formed; reinforcing placed.
  • Construction dewatering continues with regular sampling.

Caisson Installation at Southeast Corner of Garage

Lincoln Building North Entry Columns

Garage Foundation Wall Construction

Garage Elevator and Stairwell Construction

Caisson Installation along Cleveland for Garage

Lincoln Building First Floor Column Construction


The Foundry - UPDATE August 15th, 2016 - September 2nd, 2016

What will you see? (Weeks 12 - 14)

  • The two car garage that is currently sitting on 2nd Ave will be transported off site by Powell Moving on August 14th around 2:00 AM (Traffic Notice).
  • The four car garage that is currently sitting on 2nd Ave will be transported off site by Powell Moving on August 21st around 2:00 AM (Traffic Notice).
  • The Contractor will be repairing the sidewalk on the North border of 216 E. 3rd Street (old tire center) along with minor repairs to East 3rd St.  This sidewalk will be closed from August 22 to August 26.  Traffic control measures will be in place during the street repair.   The 5 parking stalls on the North border of the 216 E 3rd property will be roped off until the work is completed.  (Traffic Notice).
  • 216 E. 3rd Street lot will be converted back into a temporary parking lot.
  • All the land in-between Opera Alley and 1st Street will be seeded for erosion control
  • Final site fencing shall be installed around the first week of September.
     
    The ‘NON-EMERGENCY” contact number for the project is:  720-505-8776. There is a recording that is answered “Stephen P. Di Nardo Consulting Project Information Line – please leave a detailed message and someone will get back to you within 24 hours.

The Foundry - Update July 25, 2016

What will you see? (Week 10)

  • The demolition of the old tire center located at 216 E 3rd Street
  • The demobilization of the job trailer located at 216 E 3rd Street.  The DiNardo Management Group and Hudspeth will move into 320 N Cleveland Avenue for the remainder of the project.  The job trailer will be removed sometime between July 18th and July 29th.
  • The Environmental Abatement phase of the project is now complete.
  • There are no anticipated traffic control measures.

The NON-EMERGENCY contact number is 720-505-8776.  This is a recording that is answered “Stephen P. DiNardo Consulting Project Information Line”.   Please leave a message and we will get back to you within 24 hours.  This is a project contact line. 


The Foundry - UPDATE  July 18, 2016

What will you see? (Week 9) 

Traffic Notice: 

Project crews will be working in Lincoln Avenue again on the 20th to complete the sewer disconnection.  

The NON-EMERGENCY” contact number is 720-505-8776.  There is a recording that will be answered “Stephen P. Di Nardo Consulting Project Information Line”.  Please leave a message and they will get back to you within 24 hours.


The Foundry - update May 30th, 2016 - June 10th, 2016

What will you see? (Week 3 - 4) DEMO!

What the public will see:

  • The Contractor will be mobilizing 1 or 2 excavators and begin work on the sanitary sewer line decommission.
  • The Contractor will continue the environmental remediation of all properties.
  • The Contractor will begin removing all the tree stumps.

There are no anticipated traffic control measures.
 
NON-EMERGENCY Contact Number: 720-505-8776
This is a recording that is answered, “Stephen P. Di Nardo Consulting Project Information Line. Please leave a message and we will get back to you within 24 hours.


The Foundry - Update May 18, 2016

The KUSA-9News story on the South Catalyst project that ran three times last night. 

Reporter Dan Grossman was here in Loveland, in the wettest of circumstances, to cover the beginning of demolition/remediation as we described in a media release last week. Instead, he was mostly indoors (thanks to the rain!) with Mike Scholl at the Civic Center and Clay Caldwell at Mo Betta Gumbo.

Rain delays $60 million Loveland construction project


The Foundry - UPDATE May 11, 2016

What will you see?

Click here to see demolition map. Click here to download demolition map (11 MB .PDF)
Click here to see conceptual renderings under consideration.

The South Catalyst Project is underway!

The City has issued the official “Notice to Proceed” to Hudspeth and Associates, effective May 16th. 

Following are the activities that will occur in the next two weeks:

  • The contractor will be installing the perimeter fence around the construction site. 
    Please take special note of these closures and possible detours (see drawing below):
    • 2nd Avenue from Lincoln to Cleveland will be gated and closed for the duration of the project. 
    • Opera Alley from Lincoln to Cleveland will be gated and closed for the duration of the project. 
    • The perimeter fence will be set back in the 270 E 3rd Street parking lot to encompass the 12 stalls to the West and 7 additional stalls to the Southwest.  Upon completion of the demolition and asphalt repaving of the 216 E 3rd Street property, the fencing will be removed and the parking spaces will be available again.
  • The contractor will be mobilizing their job trailer to be located at 216 E 3rd Street.
  • The contractor will be mobilizing some heavy equipment.  All equipment will be kept inside their perimeter fence.
  • The contractor will be marking utility locates.
  • Consultants mobilized will include SPD Consulting (Project Manager), Pinyon Environmental, Colorado Civil Group, and SJR Environmental. 

What activities will begin?

  • The Contractor will commence the environmental remediation of all properties
  • The Contractor will start demolition of structures where no environmental abatement is required.
  • The contractor will be installing the Storm Water Management and Erosion control measures.

Special Note:
Please contact Stephen DiNardo at 720-505-8776 (NON-EMERGENCY)

This number takes you to a recording that is answered,  “Stephen P. Di Nardo Consulting Project Information Line.”  Please leave a message and you will receive a call back within 24 hours.  This same number will also be posted on project banners and noted on the project trailer.

Downtown Loveland Colorado, South Catalyst Project Map 

350 N Cleveland Ave Loveland, Colorado 80537   |   970.541.4333

Office Hours: Monday - Friday, 9:00 AM - 5:00 PM